Project Duration
Stipulated Date of Commencement
February 27 2021
Stipulated Date of Completion /
Likely Date of Completion August 26 2021
Likely Date of Completion August 26 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 291,308.00
Awarded for
₹ 291,308.00
Project highlights
Maintenance of UPS systems and servo stabilizers
Contractors
M/s. Dubas Engineering Pvt. Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Maintenance works at Goa Medical College and Hospital, including Hospitals and Health Centres under the jurisdiction of Goa Medical College S.H.:Supply, Installation, Testing and Commissioning of Audio Power Amplifiers for Lecture Halls 4, 5 & 6 at Goa Medical College
View Project
Supply, Installation, Testing and Commissioning of computer network with hardware and software.
View Project
Supply & Installation of Lead Doors & Lead Glass
View Project





