Project Duration
Stipulated Date of Commencement January 25 2011
Stipulated Date of Completion /
Likely Date of Completion
March 24 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,111,563.46
Awarded for ₹ 2,339,294.15

Project highlights

The work includes construction of soak pit, overhead water tank , connection of GI pipe from overhead tank to soak pit, laying of GI pipeline, providing and laying 80 mm thick factory made cement concrete interlocking paver blocks, etc

 
Gallery Image
Contractors
M/s. My Associates
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHC’s, PHC’s, RMD’s under Directorate of Health Services in North Goa – S.H. Replacement of phase barrier sheets in HT panel of Megawin make and one time servicing of 33 KV HT outdoor breaker installed at Sub District Hospital, Ponda – Goa

View Project
Similar Project

Upgradation and extension of existing Cottage Hospital at Chicalim, Goa – (120 Bedded Cottage Hospital, Chicalim) Civil, Plumbing, Electrical, Firefighting, HVAC, Lifts and Land development works

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Repair of Chilled Water Type Cassette Units installed in OPDs and an AHU installed for an Operation Theatre at Sub District Hospital, Ponda Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.