Project Duration
Stipulated Date of Commencement
January 25 2011
Stipulated Date of Completion /
Likely Date of Completion March 24 2011
Likely Date of Completion March 24 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,111,563.46
Awarded for
₹ 2,339,294.15
Project highlights
The work includes construction of soak pit, overhead water tank , connection of GI pipe from overhead tank to soak pit, laying of GI pipeline, providing and laying 80 mm thick factory made cement concrete interlocking paver blocks, etc
Contractors
M/s. My Associates
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects