Project Duration
Stipulated Date of Commencement
September 17 2023
Stipulated Date of Completion /
Likely Date of Completion January 15 2024
Likely Date of Completion January 15 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,363,408.00
Awarded for
₹ 1,488,131.00
Project highlights
Supply, installation, testing and commissioning of UPS.
Contractors
M/s. Powertrac Corporation
Consultants
M/s. Frischmann Prabhu I Pvt. Ltd.
See Similar Projects
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Supply, installation, testing and commissioning of new 12 V 17-18 AH SMF batteries, along with buy back of the old existing batteries for ARD system installed for lifts at Sub District Hospital, Ponda – Goa