Project Duration
Stipulated Date of Commencement December 11 2010
Stipulated Date of Completion /
Likely Date of Completion
January 09 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,425,521.00
Awarded for ₹ 1,393,190.00

Project highlights

The work includes supply of readymade furniture items.

 
Gallery Image
Contractors
M/s. Deshpande Constructions
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Demolition and reconstruction of 220 bedded hospital in place of Public Health Center – (I. D. Hospital) at Sadar Ponda Goa.

View Project
Similar Project

Landscape work

View Project
Similar Project

Construction of Yatri Niwas at GMC Complex, Bambolim, Goa -Civil, Plumbing & Internal Electrical works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.