Project Duration
Stipulated Date of Commencement September 18 2013
Stipulated Date of Completion /
Likely Date of Completion
November 17 2013
Status
100%
Completed
Cost (₹)
Awarded for ₹ 5,500,000.00

Project highlights

SITC of UPS systems at GMC

 
Gallery Image
Contractors
M/s. Accutech Power Solutions Pvt. Ltd.
Gallery Image
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Maintenance/Renovation works of Community Health Centre at Valpoi . Maintenance Contract for 2 Nos lift of make M/s. Thyssenkrupp Elevators India for a period of three years.

View Project
Similar Project

Construction of Community Health Centre at Canacona

View Project
Similar Project

Operation and maintenance of centralized air conditioning plant of Goa Medical College & Hospital – Replacement of AHUs.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.