Project Duration
Stipulated Date of Commencement
January 03 2014
Stipulated Date of Completion /
Likely Date of Completion March 03 2014
Likely Date of Completion March 03 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,840,000.00
Awarded for
₹ 18,340,000.00
Contractors
M/S. S. P. DISTRIBUTORS
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for the Schindler make elevators installed at Medicine Ward Block for a period of one year (2020-2021).
View Project
Renovation/ Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Servicing of installed HVAC Water line for Chillers installed at Sub District Hospital, Ponda Goa
View Project
Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim – Goa- SH-Supply, Installation, Testing and Commissioning of Operation Table
View Project