Project Duration
Stipulated Date of Commencement
December 22 2013
Stipulated Date of Completion /
Likely Date of Completion February 20 2014
Likely Date of Completion February 20 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,739,427.00
Awarded for
₹ 8,381,689.88
Contractors
M/s. OVERSEAS ASSOCIATES
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Supplying Installation Testing & Commissioning of 33 KV VCB Isolation at Substation for Electrical Supply.
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – SH: Dismantling and buy back of existing Sewage Treatment Plant (STP) and Design, Supply, Installation, Testing and Commissioning of new 30 KLD STP at Community Health Centre, Canacona – Goa
View Project
Repairs / Upgradation & Maintenance of Old Primary Health Centre at Sanquelim, Goa – Civil, Plumbing & Electrical works
View Project