Project Duration
Stipulated Date of Commencement
December 22 2013
Stipulated Date of Completion /
Likely Date of Completion February 20 2014
Likely Date of Completion February 20 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,739,427.00
Awarded for
₹ 8,381,689.88
Contractors
M/s. OVERSEAS ASSOCIATES
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Supply, installation, testing and commissioning of 13 Passenger with Stretcher Lifts at TB and Chest Disease Hospital, St.Inez – Goa
View Project
External electrical work
View Project
Fire Fighting works.
View Project