Project Duration
Stipulated Date of Commencement
October 18 2013
Stipulated Date of Completion /
Likely Date of Completion December 17 2013
Likely Date of Completion December 17 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,286,232.00
Awarded for
₹ 4,264,000.00
Contractors
M/s. Megastar Engineering
Consultants
In-house (GSIDC)
See Similar Projects
Providing of split air conditioners.
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, and RMDs under Directorate of Health Services in North Goa –S.H : Maintenance/Renovation work of Community Health Centre at Bicholim – AMC for 200kVA Transformer at CHC Bicholim for 3 years (2019-2022).
View Project
Electrical work.
View Project