Project Duration
Stipulated Date of Commencement
February 23 2008
Stipulated Date of Completion /
Likely Date of Completion May 07 2008
Likely Date of Completion May 07 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,927,260.38
Awarded for
₹ 27,788,946.00
Contractors
M/s. Knchan Associates
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd