Project Duration
Stipulated Date of Commencement
June 17 2006
Stipulated Date of Completion /
Likely Date of Completion June 16 2007
Likely Date of Completion June 16 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 118,993,540.00
Awarded for
₹ 135,678,880.00
Contractors
M/s. Eagle Construction Co.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Sub Works
This project involved 2 sub works. The details of the same available below
1
Furniture works
100% completed
Project Duration
Stipulated Date of Commencement
February 23 2008
Stipulated Date of Completion /
Likely Date of Completion May 07 2008
Likely Date of Completion May 07 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,927,260.38
Awarded for
₹ 27,788,946.00
Contractors
M/s. Knchan Associates
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
2
Providing of split air conditioners.
100% completed
Project Duration
Stipulated Date of Commencement
October 23 2008
Stipulated Date of Completion /
Likely Date of Completion November 06 2008
Likely Date of Completion November 06 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 726,404.00
Awarded for
₹ 762,190.00
Contractors
M/s. Blue Star Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Interiors (Loose Furniture Works)
View Project
Supply, Installation, Testing and Commissioning of Echo machines.
View Project
Construction of Library Block at Goa Medical College Complex, Panaji, Goa.
View Project





