Project Duration
Stipulated Date of Commencement
June 17 2006
Stipulated Date of Completion /
Likely Date of Completion June 16 2007
Likely Date of Completion June 16 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 118,993,540.00
Awarded for
₹ 135,678,880.00
Contractors
M/s. Eagle Construction Co.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Sub Works
This project involved 2 sub works. The details of the same available below
1
Furniture works
100% completed
Project Duration
Stipulated Date of Commencement
February 23 2008
Stipulated Date of Completion /
Likely Date of Completion May 07 2008
Likely Date of Completion May 07 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,927,260.38
Awarded for
₹ 27,788,946.00
Contractors
M/s. Knchan Associates
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
2
Providing of split air conditioners.
100% completed
Project Duration
Stipulated Date of Commencement
October 23 2008
Stipulated Date of Completion /
Likely Date of Completion November 06 2008
Likely Date of Completion November 06 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 726,404.00
Awarded for
₹ 762,190.00
Contractors
M/s. Blue Star Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Supplying Installation Testing & Commissioning of 33 KV VCB Isolation at Substation for Electrical Supply.
View Project
Renovation/ Maintenance of Hospitals, CHCs, PHC’S, RMD’s under Directorate of Health Services in South Goa – S.H- Renovation/ Maintenance work of Primary Health Centre at Shiroda:Maintenance Contract of the Otis Make Passenger Elevator installed at PHC, Shiroda for the period of three years
View Project
Construction of Day Care Centre at Instuitute Psychiatry and Human Behaviour Complex (IPHB), Bambolim Goa
View Project