Project Duration
Stipulated Date of Commencement August 01 2019
Stipulated Date of Completion /
Likely Date of Completion
August 10 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,528,091.00
Awarded for ₹ 12,883,641.47

Project highlights

Sewage treatment plant

 
Gallery Image
Contractors
M/s. Raveena Watertech,
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Lift work.

View Project
Similar Project

Supply, Testing and Commissioning of Ventilators with Humidifiers

View Project
Similar Project

Full Renovation And Part Construction Of The Old Heritage Building Of Asilo Hospital For State Health Training Institute At Mapusa. SH – External Lighting Work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.