Project Duration
Stipulated Date of Commencement
September 17 2015
Stipulated Date of Completion /
Likely Date of Completion March 16 2017
Likely Date of Completion March 16 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 164,370,587.00
Awarded for
₹ 167,497,585.14
Project highlights
The Existing Resident Medical Officers Hostel is proposed to be extended with a connecting corridor at first floor level, the extension building has 80 single occupancy rooms and 24 double occupancy rooms, canteen and library rooms etc.
Contractors
M/s. Shreejikrupa Buildcon Ltd
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Sub Works
This project involved 3 sub works. The details of the same available below
1
Extension of R.M.O Hostel at Goa Medical College and Hospital, Bambolim, Goa S.H.: Supply, Installation, Testing and Commissioning of 11KV 4 Way outdoor type RMU and other allied works
100% completed
Project Duration
Stipulated Date of Commencement
September 14 2018
Stipulated Date of Completion /
Likely Date of Completion November 13 2018
Likely Date of Completion November 13 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 775,410.00
Awarded for
₹ 719,999.00
Project highlights
SITC of 11KV 4 Way outdoor type RMU and other allied works at R.M.O Hostel at Goa Medical College.
Contractors
M/s. Volton Engineering (I) Pvt. Ltd.,
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
2
Extension of R.M.Os Hostel at Goa Medical College and Hospital, Bambolim, Goa – Sewage Treatment Plant
100% completed
Project Duration
Stipulated Date of Commencement
August 01 2019
Stipulated Date of Completion /
Likely Date of Completion August 10 2019
Likely Date of Completion August 10 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,528,091.00
Awarded for
₹ 12,883,641.47
Project highlights
Sewage treatment plant
Contractors
M/s. Raveena Watertech,
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
3
Extension of R.M.O Hostel at Goa Medical College and Hospital, Bambolim, Goa S.H.: Interior, Furniture works
100% completed
Project Duration
Stipulated Date of Commencement
November 09 2018
Stipulated Date of Completion /
Likely Date of Completion March 08 2019
Likely Date of Completion March 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 22,119,472.00
Awarded for
₹ 17,220,494.00
Project highlights
Providing furniture and interior works at RMO Hostel at GMC.
Contractors
M/s.Virender Kumar & Co.
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Interior Works
View Project
Air Conditioning.
View Project
External electrical works at area around new Library Building and Power supply to new Library building at GMC Complex.
View Project