Project Duration
Stipulated Date of Commencement
January 25 2007
Stipulated Date of Completion /
Likely Date of Completion November 24 2007
Likely Date of Completion November 24 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 39,118,679.00
Awarded for
₹ 42,524,358.16
Project highlights
Demolition of old structures and construction of new RCC structure, supply & installation of c-tech machinery and upgradation of existing units.
Contractors
M/s. Gharpure Engineering and Constructions Pvt. Ltd.
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
See Similar Projects
Electrical & Fire Fighting work.
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – S.H- Maintenance /Renovation work of Community Health Center at Canacona – Maintenance Contract for Schindler Elevator installed at Canacona CHC
View Project
– Supply, Installation, Testing & Commissioning of Solar Water Heating System”.
View Project