Project Duration
Stipulated Date of Commencement
December 30 2005
Stipulated Date of Completion /
Likely Date of Completion March 29 2006
Likely Date of Completion March 29 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 22,85,399.00
Awarded for
₹ 1,559,250.50
Project highlights
The work includes supply, installation, testing and commissioning of AC.
Contractors
M/s. L. G. Electronics (I) Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd