Project Duration
Stipulated Date of Commencement
January 05 2007
Stipulated Date of Completion /
Likely Date of Completion May 04 2007
Likely Date of Completion May 04 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 24,264,548.25
Awarded for
₹ 22,590,380.00
Contractors
M/s. Concept Creators
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd