Project Duration
Stipulated Date of Commencement
March 03 2014
Stipulated Date of Completion /
Likely Date of Completion February 09 2016
Likely Date of Completion February 09 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,89,670.00
Awarded for
₹ 10,34,205.00
Project highlights
Maintenance of landscaping works at Goa Dental College.
Contractors
M/s. Limboo Softscape,
Consultants
In-house (GSIDC)