Project Duration
Stipulated Date of Commencement July 09 2010
Stipulated Date of Completion /
Likely Date of Completion
January 08 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,905,483.00
Awarded for ₹ 61,49,091.43.

Project highlights

Thework includes additional miscellaneous works such as roof covering for the open courtyards, security cabins, electrical panel room, additional water pump, etc. for the hostel building .

 
Gallery Image
Contractors
M/s. Shilpi Constructions
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates
 
Similar Projects

See Similar Projects

Similar Project

Maintenance of hospitals CHC’s, PHC’s, RMD’s under Directorate of Health services S.H Maintenance of Split & window Air conditioning units at various location in the state of Goa for a period of 3 years.

View Project
Similar Project

Central Sterile Supply Department.

View Project
Similar Project

Supply, installation, testing and commissioning of Central Air Conditioning System for GMC Complex at Bambolim, Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.