Project Duration
Stipulated Date of Commencement January 05 2022
Stipulated Date of Completion /
Likely Date of Completion
January 14 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 25,108,748.16
Awarded for ₹ 28,284,599.49

Project highlights

Construction of sewage Treatment Plant

 
Gallery Image
Contractors
M/s.Indage Development Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. FP Project Management.
 
Similar Projects

See Similar Projects

Similar Project

Construction of compound wall for the Goa Medical College, Hospital at Bambolim, Goa.

View Project
Similar Project

Landscape work

View Project
Similar Project

Supplying Installation Testing & Commissioning of 33 KV VCB Isolation at Substation for Electrical Supply.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.