Project Duration
Stipulated Date of Commencement
August 19 2018
Stipulated Date of Completion /
Likely Date of Completion February 18 2019
Likely Date of Completion February 18 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 73,754,252.00
Awarded for
₹ 72,280,905.00
Contractors
M/s. Mediconz International
Consultants
M/s. KICONS Limited