Project Duration
Stipulated Date of Commencement April 15 2022
Stipulated Date of Completion /
Likely Date of Completion
December 14 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 32,678,364.00
Awarded for ₹ 36,058,328.56

Project highlights

Development of parking space

 
Gallery Image
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. KICONS Limited
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals CHC’s, PHC’s, RMD’s under Directorate of Health Services in South Goa- S.H.- Renovation/Maintenance work of primary Health Centre at Shiroda – Annual Maintenance contract of 320 KVA DG Set for Three years.

View Project
Similar Project

Site development and Landscaping at area around New Library Building GMC Complex, Bambolim, Goa.

View Project
Similar Project

Maintenance contract for elevator at CHC Bicholim for 5 years.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.