Project Duration
Stipulated Date of Commencement
April 15 2022
Stipulated Date of Completion /
Likely Date of Completion December 14 2022
Likely Date of Completion December 14 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 32,678,364.00
Awarded for
₹ 36,058,328.56
Project highlights
Development of parking space
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
M/s. KICONS Limited
See Similar Projects
Demolition and construction of hospital and hostel at Mandur, Goa
View Project
Repairs / Upgradation & Maintenance of Old Primary Health Centre at Sanquelim, Goa – Civil, Plumbing & Electrical works
View Project
Construction of subway at Bambolim
View Project





