Project Duration
Stipulated Date of Commencement November 06 2009
Stipulated Date of Completion /
Likely Date of Completion
July 05 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,926,785.00
Awarded for ₹ 5,308,124.00

Project highlights

Electrical works

 
Gallery Image
Contractors
M/s. Sunshine Electric Co. Pvt. Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – S.H- Maintenance /Renovation work of Community Health Center at Canacona – Maintenance Contract for Schindler Elevator installed at Canacona CHC

View Project
Similar Project

Furniture and Acoustical work.

View Project
Similar Project

Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri .SH- Upgradation of Wards Nos 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College & Hospitals at Bambolim ,Goa – Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim.- Office Furniture

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.