Project Duration
Stipulated Date of Commencement
October 05 2010
Stipulated Date of Completion /
Likely Date of Completion April 04 2011
Likely Date of Completion April 04 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,486,902.00
Awarded for
₹ 30,876,389.38
Project highlights
Repairs works of various wards and OT’s
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd