Project Duration
Stipulated Date of Commencement October 29 2019
Stipulated Date of Completion /
Likely Date of Completion
January 08 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 917,160.00
Awarded for ₹ 882,270.00
 
Gallery Image
Contractors
M/S. Power Engineering (India) Pvt Ltd
Gallery Image
Consultants
In-house (GSIDC)
 