Project Duration
Stipulated Date of Commencement
July 02 2010
Stipulated Date of Completion /
Likely Date of Completion January 01 2011
Likely Date of Completion January 01 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,064,138.00
Awarded for
₹ 2,909,220.00
Project highlights
False ceiling works
Contractors
M/s. Deshpande Constructions
Consultants
M/s Effective Architectural Services