Project Duration
Stipulated Date of Commencement
June 26 2009
Stipulated Date of Completion /
Likely Date of Completion January 25 2010
Likely Date of Completion January 25 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,52,760.00
Awarded for
₹ 5,122,999.00
Contractors
M/s. Mohan Electricals
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
Demolition and construction of hospital and hostel at Mandur, Goa
View Project
Upgraded Sub Health Centre at Paliyem village in Pernem Taluka.
View Project
Power Supply.
View Project