Project Duration
Stipulated Date of Commencement October 21 2011
Stipulated Date of Completion /
Likely Date of Completion
December 20 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 410,414.00
Awarded for ₹ 482,000.00
 
Gallery Image
Contractors
M/s. MegaStar Engineering
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 