Project Duration
Stipulated Date of Commencement
October 21 2011
Stipulated Date of Completion /
Likely Date of Completion December 20 2011
Likely Date of Completion December 20 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 410,414.00
Awarded for
₹ 482,000.00
Contractors
M/s. MegaStar Engineering
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.