Project Duration
Stipulated Date of Commencement
May 18 2020
Stipulated Date of Completion /
Likely Date of Completion May 17 2023
Likely Date of Completion May 17 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 938,385.00
Awarded for
₹ 938,385.00
Project highlights
AMC of HVAC System
Contractors
M/s. Voltas Limited
Consultants
In-house (GSIDC)
See Similar Projects
Medical gases & vacuum plant.
View Project
Sewage treatment plant at 30 KLD capacity
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – SH: Dismantling and buy back of existing Sewage Treatment Plant (STP) and Design, Supply, Installation, Testing and Commissioning of new 30 KLD STP at Community Health Centre, Canacona – Goa