Project Duration
Stipulated Date of Commencement July 07 2011
Stipulated Date of Completion /
Likely Date of Completion
August 05 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 402,850.00
Awarded for ₹ 407,375.00

Project highlights

Solar water heating system for bathrooms

 
Gallery Image
Contractors
M/s. B. R. Enterprises
Gallery Image
Consultants
Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of IInd Phase of Goa Dental College and Hospital at Bambolim, Goa – Furniture, Interior & Miscellaneous Works.

View Project
Similar Project

DG work.

View Project
Similar Project

Supply, Installation and Testing and Commissioning of Blood warmer

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.