Project Duration
Stipulated Date of Commencement February 17 2011
Stipulated Date of Completion /
Likely Date of Completion
July 16 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,087,400.00
Awarded for ₹ 2,220,000.00
 
Gallery Image
Contractors
M/s. Eagle Construction Co.
Gallery Image
Consultants
Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

UPS works.

View Project
Similar Project

Landscaping works

View Project
Similar Project

Electrical Works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.