Project Duration
Stipulated Date of Commencement
September 10 2006
Stipulated Date of Completion /
Likely Date of Completion December 09 2006
Likely Date of Completion December 09 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,247,890.00
Awarded for
₹ 1,654,105.00
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates