Project Duration
Stipulated Date of Commencement
December 30 2005
Stipulated Date of Completion /
Likely Date of Completion March 30 2006
Likely Date of Completion March 30 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,998,478.00
Awarded for
₹ 2,123,561.34
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Madhav Kamat & Associates