Project Duration
Stipulated Date of Commencement
December 27 2021
Stipulated Date of Completion /
Likely Date of Completion June 26 2022
Likely Date of Completion June 26 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 29,921,594.28
Awarded for
₹ 31,988,644.00
Project highlights
Providing Hospital Furniture, Kitchen Equipment and other Interior works
Contractors
M/s. Concept Creators
Consultants
M/s. Saolapurkar and Associates