Project Duration
Stipulated Date of Commencement
June 12 2020
Stipulated Date of Completion /
Likely Date of Completion August 11 2020
Likely Date of Completion August 11 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 650,402.00
Awarded for
₹ 554,710.00
Project highlights
Supply, Installation, Testing & Commissioning of CCTV system at Sub-District Hospital, Chicalim
Contractors
M/s. Geeta Automation Technologies
Consultants
In-house (GSIDC)