Project Duration
Stipulated Date of Commencement
February 07 2019
Stipulated Date of Completion /
Likely Date of Completion June 06 2019
Likely Date of Completion June 06 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,568,649.00
Awarded for
₹ 6,686,897.40
Project highlights
Office furniture and miscellaneous works.
Contractors
M/s. Virender Kumar & Co.,
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Maintenance /Renovation Work of Sub District Hospital at Ponda, Goa – Supply, Installation, Testing and Commissioning of SMF batteries including buyback of old SMF batteries
View Project
Renovation/ Maintenance of Hospitals, CHCs, PHCs, RMDs, under Directorate of Health Services in North, Goa – SH : Repair of two nos. of 60 KVA UPS installed at Sub District Hospital, Po+C523nda, Goa.
View Project
Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa
View Project