Project Duration
Stipulated Date of Commencement
June 28 2012
Stipulated Date of Completion /
Likely Date of Completion July 27 2012
Likely Date of Completion July 27 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,408,454.00
Awarded for
₹ 3,977,777.00
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Keni & D’Souza