Project Duration
Stipulated Date of Commencement
November 03 2011
Stipulated Date of Completion /
Likely Date of Completion December 17 2011
Likely Date of Completion December 17 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,387,133.00
Awarded for
₹ 2,011,550.00
Contractors
M/s. Concept Creators
Consultants
M/s. Keni & D’Souza