Project Duration
Stipulated Date of Commencement
November 20 2019
Stipulated Date of Completion /
Likely Date of Completion October 12 2019
Likely Date of Completion October 12 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 62,560.00
Awarded for
₹ 62,560.00
Contractors
M/s.Pristine Engg Services
Consultants
In-house (GSIDC)