Project Duration
Stipulated Date of Commencement
June 12 2018
Stipulated Date of Completion /
Likely Date of Completion December 26 2018
Likely Date of Completion December 26 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 144,600.00
Awarded for
₹ 144,600.00
Contractors
M/s.Nupur Technologies Pvt Ltd
Consultants
In-house (GSIDC)