Project Duration
Stipulated Date of Commencement
January 02 2012
Stipulated Date of Completion /
Likely Date of Completion March 01 2012
Likely Date of Completion March 01 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3.00
Awarded for
₹ 27,034,799.66
Contractors
M/s. Concept Creators
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.