Project Duration
Stipulated Date of Commencement
March 03 2007
Stipulated Date of Completion /
Likely Date of Completion April 02 2009
Likely Date of Completion April 02 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 174,969,028.00
Awarded for
₹ 186,209,408.98
Project highlights
RCC five storeyed building.
Ground Floor : Casualty ward & morgue, O.T.
First Floor : Consulting rooms.
Second Floor : Surgical wards, OT (04 nos.), ICU.
Third Floor : Pediatric wards, gynecology wards, antenatal ward, post natal wards, OT, special & twin private rooms.
Fourth Floor : Medicine Ward (Male & Female), ICCU, Conference Room.
Contractors
M/s. IVRCL Infrastructure & Projects Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Upgradation and extension of existing Cottage Hospital at Chicalim, Goa – (120 Bedded Cottage Hospital, Chicalim) Civil, Plumbing, Electrical, Firefighting, HVAC, Lifts and Land development works
View Project
Site development and hard landscaping of area around OPD, Casualty, Ward block and Courtyards at GMC, Bambolim, Goa.
View Project
Interior works – Phase I.
View Project