Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion May 07 2019
Likely Date of Completion May 07 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,305,526.00
Awarded for
₹ 4,299,500.00
Project highlights
Supply, Installation, Testing & Commissioning of 500KVA DG set
Contractors
M/S. Power Engineering (India) Pvt Ltd
Consultants
In-house (GSIDC)