Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion May 07 2019
Likely Date of Completion May 07 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,305,526.00
Awarded for
₹ 4,299,500.00
Project highlights
Supply, Installation, Testing & Commissioning of 500KVA DG set
Contractors
M/S. Power Engineering (India) Pvt Ltd
Consultants
In-house (GSIDC)
See Similar Projects
HVAC Works.
View Project
Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri .SH- Upgradation of Wards Nos 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College & Hospitals at Bambolim ,Goa – Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim.- Office Furniture