Project Duration
Stipulated Date of Commencement October 15 2006
Stipulated Date of Completion /
Likely Date of Completion
July 14 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 15,627,955.00
Awarded for ₹ 15,186,060.00
 
Gallery Image
Contractors
M/s. Friends Engineering Corporation
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Upgraded Sub Health Centre at Paliyem village in Pernem Taluka.

View Project
Similar Project

Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Lecture Hall Elevator and Girls Hostel Elevator installed at Goa Medical College and Hospital, Bambolim for three years (2018-2021).

View Project
Similar Project

Supply, Installation, Testing and Commissioning of ACT machine

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.