Project Duration
Stipulated Date of Commencement
October 02 2006
Stipulated Date of Completion /
Likely Date of Completion July 01 2007
Likely Date of Completion July 01 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,654,000.00
Awarded for
₹ 13,017,000.00
Contractors
M/s. Thyssenkrupp Elevators India Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.