Project Duration
Stipulated Date of Commencement
April 26 2008
Stipulated Date of Completion /
Likely Date of Completion June 24 2008
Likely Date of Completion June 24 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,378,896.00
Awarded for
₹ 26,653,000.00
Contractors
M/s. Genuine Medica Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.