Project Duration
Stipulated Date of Commencement June 21 2008
Stipulated Date of Completion /
Likely Date of Completion
August 04 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,783,101.00
Awarded for ₹ 1,872,218.00
 
Gallery Image
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Fire fighting, fire alarm and PA System works

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Hospital Furniture

View Project
Similar Project

Supply, installation, testing and commissioning of Central Air Conditioning System for GMC Complex at Bambolim, Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.