Project Duration
Stipulated Date of Commencement
October 11 2018
Stipulated Date of Completion /
Likely Date of Completion October 20 2021
Likely Date of Completion October 20 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,968,255.00
Awarded for
₹ 6,026,750.00
Contractors
M/s. Supercool Refrigeration Industries
Consultants
In-house (GSIDC)