Project Duration
Stipulated Date of Commencement
October 17 2011
Stipulated Date of Completion /
Likely Date of Completion February 16 2012
Likely Date of Completion February 16 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,834,743.14
Awarded for
₹ 2006449.53
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates