Project Duration
Stipulated Date of Commencement
May 05 2011
Stipulated Date of Completion /
Likely Date of Completion October 05 2011
Likely Date of Completion October 05 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,683,732.52
Awarded for
₹ 6086790.88
Contractors
M/s. M. M. Naik & Co.
Consultants
M/s. Datta Kare Associates