Project Duration
Stipulated Date of Commencement
May 25 2011
Stipulated Date of Completion /
Likely Date of Completion September 25 2011
Likely Date of Completion September 25 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,882,049.00
Awarded for
₹ 4157111.35