Status
100%
Completed
Contractors
Consultants
Sub Works
This project involved 6 sub works. The details of the same available below
1
Construction of Anganwadi Centres from NABARD Assistance – Package II (GPS Sangao Ozari, GPS Sakral Torse).
100% completed
Project Duration
Stipulated Date of Commencement
May 25 2011
Stipulated Date of Completion /
Likely Date of Completion September 25 2011
Likely Date of Completion September 25 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,882,049.00
Awarded for
₹ 4157111.35
Contractors
M/s. Rakesh Bandekar,
Consultants
M/s. Datta Kare Associates
2
Construction of Anganwadi Centres from NABARD Assistance – Package III (GPS Pernem, GPS Mandrem, GPS Korgao).
100% completed
Project Duration
Stipulated Date of Commencement
December 29 2011
Stipulated Date of Completion /
Likely Date of Completion July 28 2012
Likely Date of Completion July 28 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,526,892.00
Awarded for
₹ 7179487.8
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
3
Construction of Anganwadi Centres from NABARD Assistance – Package IV (GPS Chandel, GPS Ibrampur, GPS Hansapur).
100% completed
Project Duration
Stipulated Date of Commencement
May 05 2011
Stipulated Date of Completion /
Likely Date of Completion October 05 2011
Likely Date of Completion October 05 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,683,732.52
Awarded for
₹ 6086790.88
Contractors
M/s. M. M. Naik & Co.
Consultants
M/s. Datta Kare Associates
4
Construction of Anganwadi Centres from NABARD Assistance – Package V (GPS Kajrechi Vhali, GPS Dhangarwada Bhuipal, GPS Ghoteli No.1)
100% completed
Project Duration
Stipulated Date of Commencement
December 28 2010
Stipulated Date of Completion /
Likely Date of Completion March 28 2011
Likely Date of Completion March 28 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,166,556.00
Awarded for
₹ 6632510.73
Contractors
M/s. M. M. Naik & Co.
Consultants
M/s. Datta Kare Associates
5
Construction of Anganwadi Centres from NABARD Assistance – Package VI (GPS Betmoddi Kakoda, GPS Bendurdem, GPS Cumbeabhat Velim).
100% completed
Project Duration
Stipulated Date of Commencement
September 22 2011
Stipulated Date of Completion /
Likely Date of Completion June 21 2012
Likely Date of Completion June 21 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,062,925.00
Awarded for
₹ 6669089.99
Project highlights
Construction of Anganwadi Centres
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
6
Construction of Anganwadi Centres from NABARD Assistance – Package VII (GPS Bethoda).
100% completed
Project Duration
Stipulated Date of Commencement
October 17 2011
Stipulated Date of Completion /
Likely Date of Completion February 16 2012
Likely Date of Completion February 16 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,834,743.14
Awarded for
₹ 2006449.53
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
See Similar Projects
Interior, Electrical and Lift work
View Project
Repairs of Govt. Schools in Pernem Taluka – Civil, Plumbing, Electrical works – Pernem Taluka: Package – I (GPS Pokewada Morjim, GPS Kattewada Morjim, GPS Vaidongar Parse, GPS BDL Parse, GPS Harmalkarwada Tuem, GPS Parsekarwada Harmal, GPS Madhalawada Keri)
View Project
Reconstruction Of GPS at Vithalpur, Sankhalim In Bicholim Taluka.
View Project